Samsung Electronics is preparing to begin trial operations at its new semiconductor manufacturing facility in Taylor, Texas, as early as mid-to-late December, ahead of planned commercial production in 2027. The development marks a significant step in the South Korean chipmaker’s efforts to expand its semiconductor manufacturing footprint in the United States.
According to a report by The Korea Herald, Samsung has been installing manufacturing equipment, establishing production lines and conducting performance checks at the facility. Industry sources indicated that trial operations could begin around mid-to-late December, although the company has not officially confirmed a specific date.
Samsung Austin Semiconductor, the company’s US manufacturing subsidiary, is also strengthening its workforce ahead of the planned operations. The company is recruiting engineers specialising in etching, metallisation and ion implantation, along with technical instructors responsible for training new employees. These hiring activities indicate that Samsung is moving closer to operational readiness at the Taylor facility.
The preparations follow Samsung’s confirmation last month that its first Taylor plant is expected to become fully operational by the end of 2026. Company spokesperson Michele Glaze confirmed the timeline in late October, while Samsung has indicated that production will gradually ramp up in 2027.
The initial trial phase will focus on testing manufacturing equipment, validating production processes and preparing the facility for commercial-scale semiconductor manufacturing. Stabilising production yields will also be a key priority as Samsung prepares to manufacture advanced chips using its next-generation process technologies.
The Taylor facility is expected to manufacture next-generation AI6 chips for Tesla under a USD 16.5 billion supply agreement announced last year. Production of these chips is planned to begin in the second half of 2027, supporting Tesla’s growing requirements for artificial intelligence and advanced computing capabilities.
Samsung began construction of the Taylor facility in 2022, initially targeting operations in the second half of 2024. However, the project has experienced delays of approximately two years, pushing its operational timeline further into 2026 and 2027.
Alongside the first facility, Samsung is also expected to begin construction of a second manufacturing plant in Taylor this month. Announced in July, the second facility is scheduled to enter mass production in 2030.
With the Taylor project progressing towards trial operations, Samsung is strengthening its US manufacturing capabilities while positioning itself to compete in the growing market for advanced semiconductor manufacturing and AI-focused chips.